Dashboard — Café Chouchou
Project management portal · Last updated: May 2026 · All amounts in CAD
$225K
Target total financing
48 sem.
Project duration (CPM)
67
Planned tasks
4
Critical risks
Project tools
Gantt / CPM
Interactive schedule with critical path, 67 tasks, dependencies
Interactive · 76KB
WBS + Specs
3-level breakdown with specifications per work package
Interactive · 54KB
Logic Network
PDM/CPM — ES/EF/LS/LF nodes, dependencies, critical path
Zoomable · 56KB
Action Plan
63 tasks in 3 phases with observation fields and real costs
Auto-save · 50KB
Risk Analysis
18 risks analyzed — probability, impact, mitigations, residual
Filterable · 43KB
Bid Packages
5 detailed carpentry lots with contractor specs and budgets
Word · 29KB
Urgent Actions — Phase 1 (before PME MTL)
Check when complete
EnsembleLire les pages officielles pmemtl.com pour FLS et Entrepreneurship Fund — documenter les vrais chiffresFinancement
AlexCall Desjardins Business — informal CSBFP pre-qualification meetingFinancement
AlexVerify 7515 Saint-Hubert zoning online (City of Montreal portal)Espace
AlexCall an insurance broker — RC premium estimate for children's play space with custom equipmentRéglementaire
AlexCall MAPAQ Montreal (1-844-838-8003) — requirements for limited-preparation cafeRéglementaire
EnsembleVisit 2 competitor play spaces in Montreal — as parents, not entrepreneursMarché
EnsembleVilleray field visit: Tuesday morning + Saturday morning to observe family densityMarché
EnsembleGet recommendations for a PME-specialized commercial lawyer in MontrealLégal
Financing tracker (click status to update)
Confirmed$10,000 / $225,000
CSBFP — Desjardins
$130,000
PME MTL — FLS Montreal
$50,000
Entrepreneurship Fund
$25,000
Futurpreneur + BDC
$20,000
Personal investment
$10,000 ✓
TARGET TOTAL
$225,000
⬥ Confirmed ⬥ Soumis ○ En attente · Mettre à jour au fur et à mesure
Project phases
Phase 1 — Before PME MTL
Now · 4 to 6 weeks
Phase 2 — After PME MTL, before lease
Weeks 5 to 12
Phase 3 — After lease signing
Financing · RBQ permit (8 wks)
Phase 4 — Construction
~20 weeks · 5 carpentry lots
Grand Opening ★
Fall 2027 (target)
Priority risks → see all
R01 Founder capacity
R04 Summer seasonality
R05 Construction costs
R06 Optimistic revenue
R03 Multi-source financing
R09 Equipment insurance
R10 Child injury
Project documents
Interactive Gantt / CPM — 67 tasks, critical path76KBHTML
WBS with specifications — 3 levels, 67 work packages54KBHTML
Logic Network Diagram — PDM/CPM PMBOK format56KBHTML
Action Plan — 63 tâches, 3 phases, champs à documenter50KBHTML
Risk Analysis — 18 risques, matrice, mitigations43KBHTML
Bid Packages menuiserie — 5 lots avec specs contracteurs29KBDOCX
Business Plan v2 — Complete with financial projections47KBDOCX
Instructions — All files must be in the same folder
For tool navigation to work, place all HTML files in the same directory on your computer.
The action plan saves automatically in the browser (localStorage). Other tools work without saving.